IC Integrity, a joint venture between ICR and IAS (now part of UGL), delivers specialist maintenance, integrity, and inspection solutions in Australasia.
Find out more.

Category: Quickflange™ Weldless Connectors

Client: Major North Sea operator

Location: Central North Sea

Scope

Quickflange™ technology was identified to repair a leaking 4” Sch80 carbon steel nozzle feeding from a diesel tank. Hot work was not an option due to both time constraints and the extreme space restrictions with the nozzle being located in a void which was too small for a welding habitat. 

Solution

ICR’s standard installation equipment was mobilised, which was able to contend with the tight clearance, limited rigging options and space restrictions – having only limited clearance to the nearest I-beam obstruction. The technician mobilised was ‘confined space entry’ trained in order to complete the install in a safe manner. All items were mobilised within 48hours, minimising the client’s downtime. The Quickflange™ joint was also tested post installation, to ensure the integrity of the connection and that it conformed to industry and client standard.

Results & Benefits
  • No hot work 
  • Extreme space restrictions were met with no issues, something no other competitor could match 
  • Equipment mobilised 48hours from initial request 
  • Reduced cost due to minimal downtime 
ClientLocation
Major North Sea OperatorUKCS
Scope

A major North Sea Operator was required to complete a dump cooler modification scope with a 10” Cunifer seawater line during a quick turnaround shutdown scope for a Floating Storage and Offloading vessel. Pipe removal and replacement with the use of 10” 5.5mm FF Cunifer flange connections was necessary for replacement of this cooling water repair scope. Quickflange™ was the preferred choice as a cold-work application. 

Solution

 A Quickflange™ solution was delivered which had undergone leak testing, mechanical testing and burst testing to meet the required criteria for DNV Type Approval Certification. Due to time criticality and personnel limitations on board, two multi-skilled ICR technicians were mobilised to complete this scope on back-to-back day and night shifts. The highly competent technicians held the following certification: Clamshell Cutting, Advanced Quickflange™ Installations, Flange Joint Testing and MJI10 Bolting & Torquing. The technicians completed: 

  • Prepping the pipe and performing two straight cuts with clamshell cutting equipment 
  • Installation of 2 x 10” 5.5mm CuNi 90/10 16/20 Quickflange™ Connectors 
  • Flange strength testing of both connections utilising flange joint testers and ancillaries 
  • Bolting and torqueing of spools to tie-in the new pipework 

During the first of the Quickflange™ installations, the pipe was found to be oval once the cut had been performed with the clamshell cutter. This scenario can occur where the pipe ‘springs’ once the cut has been made due to tension in the pipework. The technicians used tried and tested techniques to bring the pipe to within the required outer diameter tolerances allowing the Quickflange™ to be installed. The technicians also remained to assist the shutdown team with other modification work on the asset ensuring the full scope of work planned for the shutdown was completed on time and to the highest of standards. 

Results & Benefits
  • Work successfully completed over a 3-day period; technicians on 6 back-to-back shifts cut, installed and tested the Quickflanges™ 
  • Long-term safety of system improved by permanent repair 
  • Safety, time, production and cost savings compared to conventional welding
DateClientLocation
January 2021Major O&G Company UAE
Scope

As part of a line rerouting project, a safe, reliable and fast cold work solution was required due to the complexities of the hydrocarbon condensate running through the line with 2.5 mole % of H2S (no hot work permitted). ICR were approached for the installation of a 3” 300# Quickflange™ on that line. 

Cold line isolation and cold line cutting were performed successfully in conjunction with a 3rd party contractor and a localised hydro test for the Quickflange™ joint was completed successfully to the client’s specified testing pressure. 

Significant HSE risks were a major consideration due to the line media and ensuring personnel working in the vicinity during project execution remained safe. 

Solution

After thorough engineering evaluation ICR confirmed a 3” Sch40 Carbon Steel RF 300# installation could be installed by a specialist weldless connection technician. 

After client approval, a locally based ICR technician and respective equipment was immediately mobilised to site from our local base in UAE to safely install the 3” cold connection. In conjunction with a 3rd party contractor a hydro test was successfully completed post installation. 

Results & Benefits
  • 100% Cold work installation process completed safely in less than 30 minutes by one certified local technician and one simple installation tool for that specific job 
  • ICR were able to react quickly and mobilise the Quickflange™ equipment and the manpower from its local base in UAE 
  • This subsequently allowed the operator to bring operations back on-line in short period 
  • Safety, time, production & cost savings were identified as significant benefits when compared to the conventional method of hot work and welding 

Client: Major Global Operator

Location: Gulf of Mexico

Scope

The Client wanted to use the Quickflange™ solution to complete an extension to a 12” hydrocarbon vent line on their installation in the Gulf of Mexico. 

The scope involved the installation of a 12” schedule STD 150# RF A350LF2 CS Quickflange™ onto the vent line on the platform utilising ICR’s patented Quickflange™ solution.

Solution

ICR had a qualified 12” schedule STD 150# A350LF2 CS solution within the Quickflange™ product range for the customer’s application and had the Quickflange™ & Installation tooling available to mobilise. 

The work site was situated at the top of the installation which made access to the site and the movement of the equipment to site awkward, this also meant that the available space at the worksite was limited. 

Results & Benefits
  • ICR mobilised the 12” schedule STD Quickflange™ and installation tooling from its base in Houston to the delivery point in Louisiana 
  • The ICR technician was mobilised to the platform to conduct the installation, working alongside platform personnel 
  • Once permits and lift plans were in place the pipe was cut and prepped ready for the installation 
  • The ICR technician was able to complete the installation within 1 shift and once the work site was made safe, was de-mobbed from the platform the following day 
  • Scope delivered on time, within budget and with no incidents 
DateClientLocation
May 2021BPIdku, Egypt, West Nile Delta (WND)
Scope

Due to the nature of the application and high risk associated with hot work, Quickflange™ was selected as an alternative cold work solution to carry out a tie-in for a replacement spool in an onshore refinery. 

Solution

Following the award of the scope from the client, ICR developed a virtual/online training course to train Seaharvest’s 2 technicians so they could carry out the repair. The client’s maintenance crew cut the pipe at 11am, and by 12 noon Seaharvest technicians had the flange installed. By 3pm the flange and been hydrotested to 50bar, the crew had completed the scope and left the site. 

Results & Benefits
  • Reduced down time 
  • Limited footprint of manpower onsite 
  • Large cost savings compared to the complex requirements that would have been involved with traditional hotwork with the potential for additional manpower, fire watch crews, welding habitats and NDT requirements 
  • 80% time saving