Date | Client | Location |
---|---|---|
April 2022 | EDF | North West England |
Scope
Various repairs carried out on a Carbon Steel Demin Water Reserve Feed Tank. The tank was suffering from through-wall defects due to external corrosion.
Solution
ICR were requested to provide an engineered repair solution to restore the integrity of the tank for a design life of 20 years.
Results & Benefits
- ICR provided engineering design calculation complete with design sketch, materials and manpower to complete the 8-layer repair using Technowrap™ 2K HA
- 5 x Dayshifts, 5 x repairs
- Fast & cost effective versus replacement
![](https://www.icr-world.com/wp-content/uploads/2023/04/Picture-1.jpg)
![](https://www.icr-world.com/wp-content/uploads/2023/04/Picture-2.jpg)
![](https://www.icr-world.com/wp-content/uploads/2023/04/Picture-3.jpg)
Featured articles
![Jim Beveridge, CEO](https://www.icr-world.com/wp-content/uploads/2024/02/181-scaled.jpg)
1 February | 2024
University of life stands Govan-raised engineer in good stead
![](https://www.icr-world.com/wp-content/uploads/2023/12/INSONO-scaled.jpg)
5 December | 2023
LR and UKAS boost for ICR Group’s INSONO innovation
![Northern Star 2024 Business Awards - Finalist](https://www.icr-world.com/wp-content/uploads/2023/11/1600-still.png)
17 November | 2023